NorthLight Power · Meeting brief

Development agreementA concise summary.

A staged framework to evaluate mine-site hydrogen and establish a pathway to commercialization.

Prepared 12 November 2026Torys draft · 10 November 2026
Unsigned draft · Terms remain open

The framework

Between NorthLight Properties Inc., operating as NorthLight Power Inc., and a mine operator still to be identified. It protects NorthLight’s role in subsequent commercialization but grants no mineral, extraction or production rights and creates no legal partnership or joint venture. (Arts. 1–2)

01 / Evaluation programme

Three phases. Defined decisions.

Phases 2 and 3 each require written authorization from both parties.

PhaseWork and deliverableFee and payment trigger
01

Desktop
assessment

Review geology, gas, ventilation and energy data; deliver a Data Review and Measurement Plan.

C$50,000

On the Effective Date.

02

Technical
confirmation

Low-impact gas measurements, water sampling and interpretation; deliver a Gas Measurement and Interpretation Report. No drilling or construction.

C$150,000

On authorization, before site work.

03

Commercial
pathway

Equipment, completion and production recommendations. Sustained-production verification work is excluded.

C$50,000

On delivery of the final Phase 2 Report and Phase 3 Recommendation.

Plus taxes and approved expenses. Additional work requires a signed change order.

C$250,000 if all phases are authorized

Proceed, hold or stop. MineCo decides, informed by hydrogen presence, flow and capture potential, associated gases and preliminary economics. Phases 1–2 target approximately seven weeks; Phase 3 timing is separate. NorthLight manages technical delivery; MineCo supplies data, access, site support and site-level approvals. NorthLight gives no assurance of hydrogen presence, quantity or continuity.

Articles 3–12 and 17 · Schedule A

02 / Key terms

Rights, responsibilities and protection.

NorthLight’s commercial role

Exclusivity and no-shop restrictions apply during the term and a proposed 12-month period from delivery of the Phase 2 Report, followed by a proposed 12-month right of first refusal. Non-circumvention protects NorthLight’s work; Article 13 survives termination. The geographic area remains undefined.

Articles 13 and 20

A separate development agreement

Energy-as-a-service is the anticipated model. Financing, infrastructure ownership, development rights, revenue, offtake and carbon benefits remain subject to a separate definitive agreement.

Articles 13–14

Data and intellectual property

MineCo owns raw site data. NorthLight owns interpretations and project deliverables. Reciprocal licences permit use within the purposes specified in the draft.

Article 15

Termination and liability

Either party may terminate on a proposed 30 days’ notice. Stopping an authorized phase triggers its full fee plus non-cancellable third-party commitments. Liability is generally capped at evaluation fees paid, with broad exceptions including confidentiality, exclusivity, IP and third-party indemnities.

Articles 12 and 18–20

03 / Draft status

Still to finalize.

MineCo and site details; the area and scope of protected opportunities; technical criteria and work plans; insurance; expense caps and additional-work rates; bracketed deadlines and protection periods.

Timing needs reconciliation. Section 3.4(a) requires all results within a proposed five days of the Effective Date. Schedule F places Phase 1 findings in week seven, despite their role in authorizing Phase 2.